OSCER users at OU,
*THIS MONTH ONLY*, we're expecting significantly better
pricing on condominium compute nodes and GPU nodes.
If you've got budget for condominium compute or GPU nodes,
please let me know and we'll work together on that.
We *DON'T* yet have final pricing (last year, we got it on
Jan 21).
Most likely the target date for executing a Purchase Order
will be Fri Jan 26 (certainly not later than Wed Jan 31).
---
* Condominium CPU options
Intel Xeon Ice Lake with 128, 256 or 512 GB RAM
Intel Xeon Sapphire Rapids with 256 or 512 GB RAM
(no 128 GB option)
AMD EPYC Milan with 128, 256 or 512 GB RAM
AMD EPYC Genoa with 256, 384, 512 or 768 GB RAM
* Condominium GPU options
NVIDIA RTX 6000 Ada (delivery expected within ~2 months)
NVIDIA L40S (delivery expected within ~2 months)
NVIDIA L40 (delivery expected within ~2 months)
NVIDIA H100 (delivery expect in *ROUGHLY A YEAR* --
*NOT RECOMMENDED*)
---
Director, OU Supercomputing Center for Education & Research (OSCER)
Associate Professor, Gallogly College of Engineering
Adjunct Associate Professor, School of Computer Science
OU Information Technology
The University of Oklahoma
Engineering Lab 212, 200 Felgar St, Norman OK 73019
405-325-5386 (office), 405-325-5486 (fax), 405-245-3823 (cell),
http://www.oscer.ou.edu/